  Project tasks

Purpose

The purpose of this phase is to prepare the SAP Business One system and its users for go-live.

Procedure

The following lists the tasks that have to be completed during this implementation phase.

 

Task #

Description

Results

Est. duration

Team members

1

General project management

 

3 hours

 

1-1

Confirm training plan

- Training plan and schedule confirmed and communicated to users

1.5 hours

SAP Business One project manager, SAP Business One consultant, client project manager, client IT administrator

1-2

Finalize cut-over plans

- Cut-over plan finalized and communicated to end users

1.5 hours

SAP Business One project manager, SAP Business One consultant, client project manager, client IT administrator

2

Training

 

24 hours

 

2-1

Key user training

- Key users trained

20 hours

SAP Business One consultants, IT administrator, client functional leads, client end users

2-2

Administrator training

- Administrator trained

4 hours

SAP Business One consultants, client IT administrator

3

System readiness

 

4 hours

 

3-1

Complete system administration

- All administrative settings are complete
- SAP Business One client installations are complete

2 hours

SAP Business One consultants, client IT administrator

3-2

Conduct Go-Live check

- Go-live checklist completed

2 hours

SAP Business One consultants, client IT administrator, client project manager

4

Cut-over

 

10 hours

 

4-1

Finalize legacy system processing

- Final legacy transaction and master data maintenance complete by noon of last day before cut-over
- Significant changes since last data migration run are documented and have been imported into SAP Business One

4 hours

SAP Business One consultants, client project manager, client functional leads

4-2

Conduct cut-over

- Opening balances transferred into SAP Business One system
- Pilot processes can be completed successfully in SAP Business One according to cut-over checklist
- User manuals have been created (if applicable)
- Customer has been provided with a S-number to access SAP Customer Portal

6 hours

SAP Business One consultants, client project manager, client functional leads, client IT administrator

5

Review Project Phase

- Obtain signed project phase sign-off

1 hour

SAP Business One project manager, client project manager, SAP Business One consultants

 